Laying a drive way - sub layer??

Caporegime
Joined
18 Oct 2002
Posts
37,804
Location
block 16, cell 12
hi all im laying a drive for the first time and I'm a total diy noob.

That said we've dugout 20cm deep ready to lay 15cm of sub layer. Now all the guides etc say use MOT 1 , which i understand is 40mm down to dust but is NON permeable.

Some places mention MOT 3 which is permeable - but try finding MOT 3 at any aggregate seller, its like good dust. Most haven't heard of it, so they say...only found 1 place but they want £108 per ton...with MOT 1 being like £30 per ton..

So what do people use? Mot1? Limestone 20mm?

Budget conscious but also want to do it right!
 
Caporegime
OP
Joined
18 Oct 2002
Posts
37,804
Location
block 16, cell 12
MOT1 is permeable.

Type 1

think you’re confusing permeability

Most sites say it isn't when compacted?

Screenshot-20200816-205135-Chrome.jpg
 
Soldato
Joined
6 Mar 2008
Posts
10,078
Location
Stoke area
If you're worried about it, mix MOT1 with sand, 50-50 and it'll help with the water drainage and still provide a good solid surface.

The reason MOT1 is recommended is because you're going to sticking 1+ tonne vehicles on it and it needs to be solid.

The big question is, what are you putting on the top?
 
Caporegime
OP
Joined
18 Oct 2002
Posts
37,804
Location
block 16, cell 12
If you're worried about it, mix MOT1 with sand, 50-50 and it'll help with the water drainage and still provide a good solid surface.

The reason MOT1 is recommended is because you're going to sticking 1+ tonne vehicles on it and it needs to be solid.

The big question is, what are you putting on the top?

What’s t he reason for worrying about permeability? Type 1 is used in 99% of applications with no issues.

What are you putting on top of the sub-base? If it's something like tarmac, which isn't permeable, then why would it matter if the sub-base was / wasn't?

The plan is:

Dig 20cm down - check
Lay 12-15cm of sub base - mot1/3
Install vubagrid/other brand plastic things 40mm deep with 6mm shingle in
Top layer resin bound

Put car on top:)
 